Insights · Web design

How Long Does a Website Redesign Take? Stages to Plan

The stages of a redesign in order, what makes each one run long, and what to expect from Google in the weeks after the new site goes live.

Key points
  • GoDaddy's website redesign guide estimates 4 to 6 weeks for a small site with fewer than 10 pages and limited features, 8 to 12 weeks for 10 to 50 pages or features such as forms, blogs or integrations, and 3 to 6 months for 50+ pages, ecommerce or custom development.
  • One published project guide from a university web team lists discovery at 2 to 4 weeks, planning at 4 to 6, design at 6 to 8, development at 4 to 16 and launch at 1 to 4, and says a redesign can take 6+ months for a site of that size.
  • A smaller site with one decision-maker goes through the same stages with less in each, so set your own timeline from your page count, your content and how fast you can approve work.
  • After launch, Google says crawling can take from a few days to a few weeks, and for a medium-sized site it can take a few weeks or more before the new addresses show in search.
  • Keep every redirect from an old address for at least a year, which is the minimum Google suggests.

How long does a website redesign take?

For a small business site with fewer than 10 pages and limited features, GoDaddy's website redesign guide estimates 4 to 6 weeks. A site with 10 to 50 pages, or with forms, a blog or integrations, is estimated at 8 to 12 weeks, and a site with 50+ pages, ecommerce or custom development at 3 to 6 months. What moves a project within or past those ranges is mostly the words, the photos and the approvals, because those depend on people inside the business who also have a business to run.

Treat those figures as planning ranges. A five-page site for a contractor and a two-hundred-page site with an online store go through the same stages, and the second has far more inside each one. This guide walks through the stages in order, shows two published timelines with real figures, lists what stretches a project, and covers the weeks after launch, when Google catches up with the new site.

The stages of a website redesign, in order

Every redesign runs through the same sequence. Teams name the stages differently, and the order stays the same.

StageWhat happensWhat sets the pace
DiscoveryReview what works and what does not on the current site, who the customers are, and who signs off.How quickly the right people can answer questions.
PlanningDecide the pages, the menu, the features and which old pages to keep, merge or retire.The number of pages and how many old addresses need a new home.
DesignLayouts for the phone and the desktop, starting with the home page and one service page.Rounds of feedback and how long each approval takes.
ContentWrite or rewrite the words, gather photos, and prepare anything that needs captions or descriptions.Whether the copy and photos are ready or still have to be made.
BuildTurn the approved designs into working pages, forms, booking or a store, and connect any outside systems.Features. A brochure site builds faster than one with logins, payments or integrations.
Testing and launchCheck every page on real phones, test forms and redirects, then switch the site live.How many problems the tests find and how quickly they are fixed.
After launchWatch search traffic, fix broken links, and confirm Google is picking up the new pages.Google's crawl, which you can prompt and cannot control.

Content and build can run at the same time once the designs are approved, which is the easiest place to save time. If the words are ready when the developer needs them, the build is not left waiting.

Published redesign timelines, and how to read them

GoDaddy's guide sorts redesigns by size. Its estimates are below, as written.

Site size in the guideWhat the guide countsEstimated timeline
Small websiteFewer than 10 pages and limited functionality4 to 6 weeks
Medium website10 to 50 pages or forms, blogs or integrations8 to 12 weeks
Large website50+ pages, ecommerce or custom development3 to 6 months
Enterprise websiteAdvanced integrations and multiple stakeholders6 to 12 months

For a breakdown by stage, the University of Arkansas web team publishes phase estimates in the project guide it gives departments planning a redesign. Its figures are below, as written.

Phase in the guideEstimate given
Discovery2 to 4 weeks
Planning4 to 6 weeks
Design6 to 8 weeks
Approvals of designVaries
Development4 to 16 weeks
Approvals of developmentVaries
Final approval and launch1 to 4 weeks, can vary

The same guide says a website redesign can take 6+ months, and that its estimates leave out choosing a designer or developer and any bidding process. Read it as the shape of a large project with many people signing off. Two of its lines say only "varies": both are approvals. Approvals vary for every business, large or small.

Most small business sites sit in the first two rows of the size table: fewer pages, fewer templates and one or two people who approve the work, so each stage holds less. The stages and their order stay the same, and the approvals are what can push a project past its row.

What stretches a redesign

The University of Arkansas guide names the problems that derailed its own projects. They are the same ones that slow a small business site.

  • Slow approvals. The guide says delays in approval time, at any phase, can derail the project, and it recommends strict approval deadlines.
  • Content that is not ready. Writing and rewriting content, and waiting on people with other priorities to supply it, were reported as major time sinks.
  • Moving old pages. Deciding which pages to keep takes time, and reworking the structure of the site is time-intensive.
  • Holidays. The guide tells teams to account for them in the schedule.
  • People and surprises. Staff turnover and unexpected technical problems were reported as derailing projects.
  • Added features mid-project. Booking, a store or a customer login added after the scope is set reopens planning, design and build.

Every item on this list comes down to planning and decisions, and the business controls most of them.

What you can do to keep the timeline short

The fastest redesigns start with the owner's homework done before the first design is drawn.

  1. Name one decision-maker. One person approves designs and pages, and agrees to answer within a set number of days.
  2. List the pages you have now. Mark each one keep, merge or retire, and note which ones bring calls today.
  3. Write the services page first. It is usually the page that matters most and the one that takes longest to get right.
  4. Gather photos early. Real photos of your work, your team and your place of business take time to collect or shoot.
  5. Freeze the feature list. Agree on booking, payments or logins in the scope, and put new ideas on a list for after launch.
  6. Pick the launch window. Choose your quiet season and work backward from it.

If you have not yet decided whether the site needs a full rebuild, our guide on when it is time to invest in a website redesign lists the signs to check first.

Launch day and the weeks after

A redesign is not finished the day the new site goes live. Google still has to find and read it, and when page addresses change, Google treats the redesign as a site move.

  • Crawling. Google says crawling can take anywhere from a few days to a few weeks. You can ask it to recrawl a few pages with the URL Inspection tool in Search Console and submit a sitemap for the rest, and it says asking repeatedly for the same page does not speed things up.
  • New addresses in search. For a medium-sized website, Google says it can take a few weeks or more before it starts showing the new addresses, and that rankings may fluctuate while it recrawls and reindexes.
  • Redirects. Google says to keep redirects for as long as possible, generally at least 1 year, and to consider keeping them for good from the visitor's side.
  • Timing. Google suggests timing a move to coincide with lower traffic where possible.

Speed numbers take time too. The Core Web Vitals report in Search Console describes its figures over the last 28 days, and when you fix an issue and start tracking it, Search Console runs a 28-day monitoring session before calling it fixed. Plan to judge the new site's speed about a month after launch. Our guide to website speed optimization in Chattanooga covers what to check.

How to set your own redesign timeline

Build the schedule backward from the date you want the new site live, using the stages above.

  1. Mark the launch window. Your quiet season, clear of holidays.
  2. Leave room after launch. Keep the weeks after go-live free of other big changes, so you can tell what the redesign did.
  3. Block time for testing. Testing on real phones and fixing what turns up comes right before launch.
  4. Place the build and content side by side. Both finish before testing starts.
  5. Set design and approval dates. Write down when each approval is due and who gives it.
  6. Start discovery and planning now. The page list and the scope come first.

Ask any team you talk to for a written schedule with these stages and the date each approval is due from you. If the price is the open question, our guides to website redesign cost in Chattanooga and how much a website costs for a small business explain what moves the number.

How Nooga Tech plans a redesign

Nooga Tech is a web design and engineering team in Chattanooga, and redesigns are part of our Web Design & Growth work. We build phone-first websites with your services, your service area, one-tap calling and a clear next step on every page.

Written scopeThe pages and features are written down with a fixed price before any work starts, so the timeline is built on a list that does not move.
Phone firstDesigns start from the phone screen, where most customers will see the site.
Built to be foundTechnical and content SEO, with every old address mapped to its new page before launch.
Yours from day oneThe domain, the code and the hosting are in your name.

Bring your list of current pages and the month you would like the new site live, and book the free 30-minute consult. We will tell you what the scope looks like and what we need from you at each stage.

Frequently asked questions

How long does a website redesign take?

GoDaddy's redesign guide estimates 4 to 6 weeks for a small site with fewer than 10 pages and limited features, 8 to 12 weeks for 10 to 50 pages or added features, and 3 to 6 months for 50+ pages, ecommerce or custom development. Content and approvals decide where a project lands.

What are the stages of a website redesign?

Discovery, planning, design, content, build, testing and launch, then the weeks after launch while Google recrawls the site. Content and build can run side by side once the designs are approved.

What makes a website redesign take longer?

Slow approvals, content that is not ready, deciding what to do with old pages, holidays, staff changes and features added after the scope is set. Most of these are decisions the business controls.

How can I speed up a website redesign?

Name one person to approve work, list your current pages, write the services page early, gather photos before the build, freeze the feature list and agree on approval dates up front.

How long does Google take to pick up a redesigned site?

Google says crawling can take from a few days to a few weeks, and for a medium-sized site it can take a few weeks or more before the new addresses show in search. Rankings may fluctuate in that period.

How long should I keep redirects after a redesign?

Google says to keep them for as long as possible, generally at least 1 year, and to consider keeping them for good for visitors who use old links.

When is the best time to launch a redesigned website?

In your quieter season. Google suggests timing a site move to coincide with lower traffic where possible, so fewer customers are affected if something needs fixing.

Does Nooga Tech give a timeline before starting?

We write the scope with a fixed price before any work starts, and we plan the stages and your approval dates from that scope. Book the free consult on our [Web Design & Growth](/marketing) page to start.